Overview
Beeshoek deployed SmartCap in 2014 to assist in gauging the fatigue risk on-site and empowering the workforce to proactively self-manage. Leading up to the deployment, the site had suffered from a number of incidents involving operators returning to work after extended periods of leave.
Outcomes
Beeshoek have seen a significant reduction in fatigue incidents on-site. Workforce engagement has greatly improved as a result of the inclusive change management process.
Challenges
- Limited literacy amongst the workforce has required a heavy emphasis on training via demonstration.
- High staff turnover makes long-term improvements difficult to guage.
-
Site Name:Assmang Beeshoek
-
Location:South Africa
-
Commodity:Iron Ore
-
Vehicles:54 haulage fleet trucks